A skid closes design, manufacture, testing and compliance in the factory; site work reduces to power, pipe and commissioning. Done well, site time drops from 3 months to 2 weeks.
- Confirm the design-input sheet (duty list, environment, utilities, transport, standards) before starting.
- Structure at 2× dynamic load for offshore; verify alignment after transport.
- Pressure vessels to GB/T 150-2024 / GB/T 151-2026 or ASME VIII; check maker licence and supervision reports.
- FAT covers airtightness, safety valves, ≥4 h load run, performance, dew point, noise, vibration, interlocks, comms.
- Deliver the MDR as a contract annex — incomplete MDR delays final payment.
Full 12-node checklist in Chinese; we issue the FAT outline for approval before testing.